Temporary Certificate Of Completion Request

A government service that enables customers to obtain a temporary certificate of completion to start connecting the building to the electrical grid. All concrete and brick works must first be completed and submitted by the consultant.

Required Documents

    Business

  • Completion certificate request form (temporary/final) approved by Ajman Sewerage

  • All building inspection reports

Process

  • 1 Submitting the service request via the Department's website by registered users.
  • 2 Paying the service fees online
  • 3 Processing the request
  • 4 If the request is approved, fees are paid, and the temporary completion certificate is received.
  • 5 If the request is rejected, the customer is notified through the system

Service fees

  • All buildings: AED 2000

  • Private villas + farms: AED 500

Service Duration

  • 2 Days